Service

Wind turbine structural inspections

CR11 statutory compliance assessment of wind turbine towers. Drone survey, structural analysis, and an ECSA-signed compliance report, scaled from a single tower to a fleet.

Method, as delivered at Garob

The working method is the one used on WTG 21 to 24 at Garob Wind Farm: methodology review, on-site structural assessment, drone survey, and an ECSA-signed compliance report.

  • CR11 / Construction Regulations duty-holder trail.
  • IEC 61400-6 structural reference where it applies.
  • Findings written so an asset manager can act, not only an analyst.

Read the Garob case note and the CR11 guide for wind IPPs.

Plan a CR11 assessment

Include the farm, turbine count, and whether this is a first assessment or a follow-up. Or email [email protected].